Tank Issue and Receipt Piping Replacement
Stratton ANGB, NY
Project Description:
This design build project was a repair/modification to an existing fuel system that had been built with aluminum piping. Through multiple drain downs and phasing, the existing tank piping was able to be upgraded to standard internally lined carbon steel piping while never taking the facility offline for more than 3 days at a time.
500 ft Carbon Steel
Piping
Fuel Farm Modifications & Repairs