Aircraft Hardstand Ramp Expansion

DFW International Airport, TX

Cover.JPG

Project Description: 

This addition to the existing fuel system was a 14” carbon steel hydrant loop expansion with 19 each – hydrant pits, 4 each – high point vents, 4 each – low point drains, and 2 each – isolation valve vaults. The expansion to the hydrant system was completed with 2 each – 20”and 2 each – 14" double stopple procedures with Plidco couplings.

4,600 ft Carbon Steel
Piping
New Hydrant Loop Addition
Project Type
airport.png

Talon has worked on over 30 different

projects at DFW Airport  