Fuel Piping Contractor

Talon has worked on multiple projects for the oil & gas industry.  Talon has built marketing terminals, pipeline terminals, tank farms, truck loading racks and barge loading docks.

Project: Construct Fuel Terminal

Location: Boligee, AL

Prime or Sub: Prime

Completed Date: June 2008

Description: Construct 5 each - gasoline and diesel fuel tanks with a total capacity of 22 million gallons, a 4500 gpm barge loading facility, 3 lane truck loading facility, 16” twin pipeline receipt manifolds, over 15,000 LF of pipe 16” and under, and associated civil, electrical, painting and other work.

Project: New Loading Rack

Location: McFarland Terminal, WI

Prime or Sub: Sub

Completed Date: May 2014

Description: Install piping for a new track loading rack.

Project: Colorado City Terminal

Location: Colorado City, TX

Prime or Sub: Sub

Completed Date: October 2014

Description: Install 24" receipt manifold piping, 24" transfer manifold piping, 24" tank piping, 2 each - booster pumps,and multiple crossover walkways.

Oil & Gas Projects