Talon has constructed pumphouses, transfer lines, hydrant loops, hydrant pits, isolation valve vaults, truck fillstands, truck unloading skids, product recovery tanks, above ground storage tanks, and underground storage tanks for commercial airports. 

Project: Construct Sunport Jet A Fuel Farm

Location: Albuquerque, NM

Prime or Sub: Sub

Completed Date: July 2006

Description: Furnish and install carbon steel piping for 3 each - 10k bbl Jet A fuel tanks, a 12” transfer line 4400 LF, 6 each - truck fillstands, 2 each - truck unloading stations, including all associated pumps, filters and miscellaneous equipment.                                                        .

Project: Terminals A and C Regating

Location: DFW Airport, TX

Prime or Sub: Sub

Completed Date: May 2011

Description: Relocate 15 each - jet fuel hydrant pits at various gates through out Terminals A and C.  All tie-in work was done over night to not disturb ongoing fueling operations. 1000 tons of soil remediation was completed. .

Project: Fuel Farm Improvements

Location: Wichita Airport, KS

Prime or Sub: Sub

Completed Date: April 2012

Description: Install 6 each - Jet A vertical turbine pumps and 2 each - Avgas submersible turbine pumps in existing underground storage tanks, install 1 each - 2500 gallon dual compartment above ground storage waste tank and 2 each truck offload stations.

Commercial Aviation Projects


Fuel Piping Contractor

Project: Fuel Farm Modifications, Terminal D and New Fuel Isolation Vaults

Location: DFW Airport, TX

Prime or Sub: Sub

Completed Date: June 2005

Description: Furnish and install piping for 2 each - 80k bbl Jet A fuel tanks, a 16” hydrant loop 4400 LF, 52 each - hydrant pits, 4 each - isolation valve pits for the new Terminal D, and replace 4 each - concrete isolation valve vaults in the AOA area.  Pipeline stopples required for the concrete isolation valve vaults.  All tie-in work was done over night to not disturb ongoing fueling operations..